Residential complex Lukomorye in Kyrenia (Alsancak)































12 June 2013

Blocks "A", "B" and "C" are ready for finishing. Completed the brickwork and finish the plastering work on the block "D". We completed the construction of the reinforced concrete frame and the brickwork of the block "E". We conduct plastering works on the block "E", after which we will begin the interior decoration of the apartments of the whole complex.



12 June 2013

Blocks "A", "B" and "C" are ready for finishing. Completed the brickwork and finish the plastering work on the block "D". We completed the construction of the reinforced concrete frame and the brickwork of the block "E". We started plastering works on the block "E", after the interior decoration of other blocks has started.


25 April 2013

Block "B". Finished plastering and putty works.

Block "C". We finished the brickwork of the walls, finish the plastering works.

Block "D". Completed reinforcement and concreting of vertical structures and floors of the building. Completed the brickwork of the walls of the first floor.

Block "E". Completed the reinforcement and concreting floors of the first floor. We make reinforcement of vertical structures of the second floor.


20 March 2013

Block "А".

Connected paths to the land and asphalt road leading to the complex.


Block "В".

We began the brickwork of the walls of the first floor of Block "C".

The reinforcement and concrete of the floors of the first floor have been completed and the vertical structures of the second floor of Block "D" were reinforced.

The reinforcement and concreting of vertical structures of the first floor of Block "E" were completed.

Attention: today's photo of the hotel's beach "Merit" (located 950 meters from the complex "Lukomorye").


23 February 2013

Completed outdoor work on the block "A". The next stage of construction will be finishing works.

Completed the brickwork and plastering work on the block "B".

We completed the construction of the reinforced concrete skeleton of the block "C". Concreting the vertical structures of the block "D".


3 January 2013

Finished plastering works, puttying the walls and installed window sills on the block "A"

Completed the construction of a reinforced concrete frames and the walls of the first floor of the "B" block.

The reinforcement of vertical structures of the 1st floor of the block "C" is completed.

The construction of the foundations of blocks "D" and "E" is being done.


10 December 2012

We finish the plastering works on the block "A".

The reinforcement and concreting of the vertical structures of the 1st and 2nd floors, reinforcement and concreting of the floor slab of the 1st floor, reinforcement of the slab of the 2nd floor of the block "B" is made. Completed work on the brickwork of the walls of the 1st floor of Block "B".

The construction of the foundations of blocks "C", "D" and "E" is being done..


7 November 2012

The reinforcement of vertical structures of the 1st floor of block "B" is completed.


31 October 2012

Completed work on the brickwork of the walls of the second floor.

Completed plastering on the interior walls of the ground floor apartments.


26 September 2012

Completed work on the brickwork of the walls of the first floor.


20 September 2012

Works on reinforcing and concreting the floor slab of the second floor of the block "A" have been completed.


11 September 2012


29 August 2012


22 June 2012

 

The project "Lukomorye" will be built in 5 blocks of apartments and 6 apartment units in each. These apartments are available for sale. At this moment, 80% of the apartments  have already been reserved by the clients. Today  the construction of the first three blocks has began. The fourth and fifth blocks are planned to start in October of this year.

 

Limited offer!
Apartments and villas in North Cyprus with discount!
When you purchase any property in North Cyprus as a gift from our company you will receive:
Set of household appliances
Registration of residence permit (residence permit)
from December 8 to January 15
discount up to
33%
Your message from the form sent
In the near future you will contact our company