Residential complex Sel Lapta in Kyrenia (Lapta)

28.07.2016

28 July 2016

Installing the most modern energy efficient windows and balcony doors with light-absorbing glass in all apartments of the complex, which will allow residents to reduce expenses for heating apartments in winter and cooling in the summer.

The entrance doors have been installed.

We installed individual vacuum solar panels for each apartment on roof terraces.Residents of the  Lapta Sel complex will be able to use hot water, heated by the energy of the sun, even in the winter time, which will also significantly reduce the cost of electricity.

Installing kitchen cabinets.


23 May 2016

Completing  interior and exterior painting in all three blocks.

Completing marble, granite and ceramic tiles on the floor and walls of all apartments in Block C. Completing individual garden terraces of ground floor apartments in all three blocks.

Completing the arrangement of individual roof terraces in last floor apartments (including hydro and thermal insulation, installing  ceramic tiles on the floor, fixing the drainage and painting of walls and partitions).

Entrances of all blocks and marble staircase in Block C has been done.


20 February 2016

Plastering of outside walls and Puttying the inner walls of the block "C" have been completed. water and electricity connections in the block "C" has been done. First layer of painting on exterior walls of the block "C" has been finished. Hydro and thermal insulation of the roof of the block "C" has been done. Started the paving slabs in the common areas and car parking of the complex.


31 January 2016

We are already at the final stage of the construction process. In blocks B and C, it is ready to install  windows, doors, kitchen cabinets and handrails, while in block A flooring with marble, ceramic granite and ceramic tiles still  being on going. further more, the final painting of buildings and the paving slabs in this complex is being done.

Video:

Photo ( pictures of Block B):

Completing marble, granite and ceramic tiles on the floor and walls of all apartments in Block B. 


10 January 2016

Installation of windows and handrails on the stairs and balconies in the block "A".

We finish the plastering works on the outer walls of the block "C".

Installing marble windowsills in block "C".

We are puttying on the inner walls of the block "C".

Plastering of outside walls and Puttying the inner walls of the block "B" have been completed. water and electricity connections in the block "B" has been done. First layer of painting on exterior walls of the block "B" has been finished. Hydro and thermal insulation of the roof of the block "B" has been done. Started the paving slabs in the common areas and car parking of the complex.

Completing  the construction of a stone fence around the complex.


9 August 2015

Completing concrete columns  and reinforced concrete of the third floor of Block "C". The brickwork of the internal and external walls of the block "C" is being strated.

We continue plastering the inner and outer walls of the block "B".

We continue finishing work in the block "A":

Completing granite and plinths on the floor of the apartments. Completing the isolation in balconies. Completing non-sliding ceramic tiles and plinths on the balconies.

Completing work on the insulation of bathrooms.

Completing ceramic tiles on the floor and walls of bathrooms. Completing the work on conducting electrical wiring, installation of water supply and sewage systems.

Marble staircases has been installed.

Completing work on the thermal insulation and waterproofing  the roof, non-sliding ceramic tiles and plinths have been installed.


12 September 2015

Completing the brickwork of the inner and outer walls of the block "C".The connection of water and electricity in blocks "B" and "C"have been done.

We finished the plastering works on the inner and outer walls of the block "B".

First layer of painting of exterior walls in the block "A" has been completed.


9 August 2015

Completing concrete structures and reinforced concrete floors of the third floor in Block "C". 

19 July 2015

Brickwork of  inner and outer walls of the block "B" has been completed. Plaster works have begun


Granite works on the floor in block "A" has been completed. 


31 May 2015

The construction process continued in block "A".




19 April 2015

We made finishing work on the block "A". We completed the construction of the reinforced concrete skeleton of Block "B". The construction of the block "C" has began.


06 March 2015

Completed work on reinforcing and concreting the floors of the 2nd floor and vertical structures of the third floor of block "B". And also completed the work on the brickwork of the inner and outer walls of the 1st floor of Block "B".


07 February 2015

Completely finished the plastering works on the outer walls of the block "A". They installed marble windowsills and completed the laying of water pipes inside the apartments of block "A". Installed sewer septic tanks outside the block "A".

Completed the work on reinforcing and concreting the floors of the 1st floor and vertical structures of the 2nd floor of block "B". We make the reinforcement of the floors of the 2nd floor of block "B".


27 December 2014

Completely finished plastering on the inner walls of the block "A". Stucco work on the outside walls of block "A" at the final stage.

Completed the work on reinforcing and concreting the vertical structures of Block "B", and also completed the work on reinforcing the floors of the 1st floor of block "B".


05 December 2015

Completed the construction of the foundation of Block "B"

Completed work on the brickwork of the internal and external walls of the block "A".

We finished plastering the inner walls of the 1st and 2nd floors of block "A".


05 November 2014

We finish the brickwork of the inner and outer walls of the 2nd floor of Block "A". And also began to plaster the walls of the 1st floor of block "A".

We began the construction of the foundation of Block "B".


13 October 2014

Completed the work on reinforcing the floors of the third floor of Block "A". And also completed the work on the brickwork of the internal and external walls of the 1st floor of Block "A".


01 October 2014

Completed the work on concreting the floors of the 2nd floor, and also completed the work on reinforcing and concreting the vertical structures and stairwell of the third floor of Block "A".

We began work on the brickwork of the inner and outer walls of the block "A".


23 September 2014

Completed the work on reinforcement of the floors of the 2nd floor of block "A".


02 September 2014

Completed the work on reinforcing and concreting the floors of the 1st floor, vertical structures and stairwell of the 2nd floor of Block "A".


12 August 2014

The reinforcement and concreting of the stairwell of the 1st floor of Block "A" were completed.

We completed the reinforcement work, and also installed the formwork of the floors of the 1st floor of Block "A".


19 July 2014

We completed foundation and also finished reinforcing and concreting the steps which are leading to the individual garden terraces of ground floor apartments. the vertical columns of 1st floor in Block "A" is being done in the same time.

Limited offer!
Apartments and villas in North Cyprus with discount!
When you purchase any property in North Cyprus as a gift from our company you will receive:
Set of household appliances
Registration of residence permit (residence permit)
from December 8 to January 15
discount up to
33%
Your message from the form sent
In the near future you will contact our company