03.03.2012
3 March 2012
The construction of the Dolce Vita 2 Resort project in Kyrenia was completed
21 January 2012
We installed windows, balcony sliding doors and aluminum railings.
Entrance doors has been installed.
Built-in wardrobes in bedrooms has been installed.
Marble stairs has been installed.
Within 3 weeks we plan to finish the construction and settle in the happy tenants in the house.
10 November 2011
Finish the plaster.
The water and electricity pipe works and connections was completed, a stone fence was built around the site, the walls were painted (under painting) and marble window sills were installed.
5 July 2011
Brick works has been completed.
12 May 2011
Frame filling has been completed.
24 March 2011
The first floor concrete floors and columns have been done.
27 January 2011
The Dolce Vita 2 Resort project was started.
All apartments in this project were reserved in 1 month, even before the construction has started. All buyers of this apartment are foreigners.